1st April 2024Stage 2, Week 2 (WC 25 March) + Week 3 Update (WC 1 April)
Hello,
Bernherd's have completed all their tasks on site prepping the surface and surroundings for the initial pour by Polytan.
However, owing to the weather at the end of WC 25 March, and the forecast for WC 1 April, the track renovations have been delayed by one week currently with a hope to commence on 8 April.
Polytan will require a period of 4-5 days dry weather for this vital next stage to prevent water being trapped between two non-porous surfaces which could result in issues with the track surface. As a result, they are cautious with this first part of the pour to ensure it adheres to the high standard required.
We continue to operate on weekly updates from both companies, and hope to have a more positive change in the weather soon!